Process timelines (approximate):
Process
Timeline
Comments
Land Use Bylaw Amendment Process
60 to 90 days
Development Permit Process
40 days
Subdivision Process
60 days
Building Permit Process
21 days
Subdivision and Development Appeal Process
- within 30 days of receipt of notice of appeal
- written decision within 15 days of concluding the hearing
for information contact 464-8140
Development Agreement Process
90 days
Area Stucture Plan
120-180 days
Note that some of these processes can occur at the
same time. Some are dependent upon municipal as well as provincial guidelines.